When developing a program charter, a program manager conducts a thorough review of the organization's internal resources and the external market landscape. What is the main purpose of this review?
To establish communication protocols among stakeholders.
To align the program with strategic objectives and identify potential challenges and opportunities.
To define the program's schedule and milestones.
To allocate resources effectively across program components.
Reviewing internal resources and the external market landscape helps align the program with strategic objectives and identify potential challenges and opportunities, ensuring the program is well-positioned for success. The other options address important program aspects but do not directly relate to strategic alignment through environmental evaluation.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is aligning a program with strategic objectives important?
Open an interactive chat with Bash
What tools or techniques are used to evaluate internal resources and the external market landscape?
Open an interactive chat with Bash
What are some examples of potential challenges a program manager might identify during this review?
Open an interactive chat with Bash
PgMP
Program Life Cycle Management
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .