PgMP Practice Question

Midway through a three-year digital-transformation program, the head of customer operations and the CFO have begun questioning whether their individual concerns-service-level KPIs and cost containment-are truly reflected in the benefits roadmap. Attendance at recent steering-committee meetings has dropped, and informal feedback suggests key stakeholders feel their voices are lost in group sessions. As the program manager, which action will most effectively rebuild their engagement and strengthen long-term stakeholder relationships?

  • Add their topics to the agenda of the next quarterly steering-committee review and request written decisions.

  • Revise the communication management plan to require distribution of detailed status reports every Friday.

  • Set up recurring individual meetings with each key stakeholder to discuss their specific concerns and agree on next steps.

  • Email a consolidated weekly dashboard to all stakeholders highlighting earned-value and milestone status.

PgMP
Stakeholder Engagement
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot