PgMP Practice Question

Midway through a multi-year transformation program, the chief marketing officer emails the program manager requesting a new customer-facing capability that will delay key milestones by three months and add significant cost. The request has not yet been entered in any tracking system. According to the approved program change management plan, what should the program manager do first?

  • Immediately convene the steering committee to decide whether to accept the new capability.

  • Direct each affected project manager to rebaseline schedules to accommodate the three-month delay.

  • Record the request in the program change log and assign an initial identifier for tracking.

  • Reject the request until the executive supplies a detailed business case and funding.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot