Midway through a multi-year digital-transformation program, the program manager learns that the first product increment will go live in two months. Operations leaders worry about ownership gaps and post-go-live defects. To minimize disruption and preserve benefits, what should the program manager ensure is in place before authorizing deployment?

  • A transition plan co-developed with operations that lists hand-over tasks, responsible owners, acceptance criteria, and 90-day support measures

  • A sign-off letter confirming the system passed initial functional testing and can be released to users

  • A lessons-learned log summarizing project execution issues for future reference

  • A vendor maintenance contract that transfers warranty responsibility immediately after development ends

PgMP
Benefits Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot