During the rollout of a new analytics platform, the program manager wants to document requirements for a vendor's system responsiveness, availability, and support. Which action helps hold the vendor accountable for delivering these obligations?

  • Incorporate specific targets, structured measurement protocols, and regular review intervals into a formal agreement with the vendor

  • Negotiate general reliability clauses in a statement of work and invite the vendor to propose corrective measures if issues arise

  • Include a concise note in the project plan acknowledging the vendor's responsibilities and use informal reminders as needed

  • Schedule routine status updates with the vendor, relying on day-to-day collaboration rather than documented requirements

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot