During the program closure phase, what is an essential action a program manager should take to ensure a smooth transition of program benefits to the operational team?
Transition ongoing activities to the operational team.
Reallocate remaining resources to other projects.
Conduct a root cause analysis on project issues.
Initiate new project charters for upcoming programs.
Transitioning ongoing activities to the operational team ensures that the benefits of the program are sustained after closure. This action aligns with best practices for program closeout by transferring responsibility and maintaining the continuity of benefits realization.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does 'transitioning ongoing activities' mean?
Open an interactive chat with Bash
Why is it important to sustain benefits after program closure?
Open an interactive chat with Bash
What are best practices for program closeout?
Open an interactive chat with Bash
PgMP
Program Life Cycle Management
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access