PgMP Practice Question

During the Monitor and Control Program Risks process, how should the program manager handle the program risk register when no new threats have been identified since the last review?

  • Skip further risk register updates and focus on issue management instead, because all risks have already been logged.

  • Archive the current risk register and start a new version only if a major change request is approved.

  • Continue to update the risk register to reflect changes in probability, impact, and status of existing risks and their responses.

  • Freeze the risk register until the next formal risk identification cycle to avoid unnecessary rework.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot