PgMP Practice Question

During the kickoff workshop for a program that will add 500 MW of new solar capacity, the operations vice-president demands aggressive construction schedules, the finance director insists on prioritizing projects with the highest short-term ROI, and the sustainability officer wants only sites meeting strict environmental certifications. Before detailed planning begins, which action should the program manager take first to keep the effort aligned with the company's strategic sustainability objectives?

  • Facilitate consensus on program objectives linked to the sustainability mission and document them in a draft program charter.

  • Produce a detailed stakeholder communication matrix indicating frequency and format of updates.

  • Allocate preliminary budgets to each project based on forecasted return on investment.

  • Develop a phased construction roadmap that compresses high-capacity sites into the first two years.

PgMP
Strategic Program Alignment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot