PgMP Practice Question

During initiation of a multi-country product-launch program, work will span data analytics, brand redesign, compliance updates, and regional promotions, each with separate sponsors and shared resources. To capture the full scope, align deliverables to strategic objectives, and assign accountability across teams before detailed scheduling, which artifact should you produce?

  • A responsibility assignment matrix that maps available roles to tasks already identified by functional managers

  • An integrated master schedule that sequences every project activity and highlights the program's critical path

  • A Kanban-style backlog that accepts tasks on demand and prioritizes them based on current constraints

  • A hierarchical work breakdown structure decomposing program deliverables into work packages with unique codes

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot