PgMP Practice Question

During delivery, a project manager submits a change request to extend the project schedule by four weeks. The delay will postpone a capability listed on the program roadmap and could defer planned benefits. According to PMI's Standard for Program Management, what is the MOST appropriate way for the program manager to handle this request?

  • Approve the request at the project level, since schedule decisions reside with the project manager.

  • Submit the request to the program's standardized change-control process for impact analysis and approval before any work is authorized.

  • Reject the request outright, because any schedule slippage violates the program baseline.

  • Implement the change immediately to avoid further delay and update documentation later.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot