PgMP Practice Question

During a mid-cycle review of a complex digital transformation program, a program manager identifies an unforeseen synergy. A data analytics module developed in Project A could be leveraged by Project B, potentially accelerating its timeline and enhancing its benefits. This action requires temporarily reallocating specialized data scientists from Project A, which may cause a minor, controlled delay to one of Project A's non-critical milestones. What is the program manager's most appropriate next action?

  • Conduct a formal impact assessment on the overall program benefits, schedule, and resources, then submit a change request to update the relevant program and project plans.

  • Present the potential synergy to the steering committee to get their direction before conducting any impact analysis or reallocating resources.

  • Immediately reallocate the data scientists to capitalize on the opportunity and report the schedule variance for Project A in the next status report.

  • Instruct the respective project managers to negotiate resource sharing and resolve the scheduling conflicts independently.

PgMP
Benefits Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot