PgMP Practice Question

A rapidly growing financial-services organization is running a multi-year Digital Transformation Program consisting of three concurrent projects: a mobile banking app, an API modernization effort, and a data-analytics platform. Each project has committed to a fixed launch date aligned to a regulatory compliance window. During the monthly steering-committee review, the Program Manager presents a timeline showing that the API modernization work is running 12 days late, the mobile app is 6 days early, and the analytics platform is exactly on schedule. Senior leadership asks whether these schedule differences are random fluctuations that can be expected at this stage or signs that individual projects need additional intervention. Before reallocating resources or approving overtime, the Program Manager decides to perform a statistical study on the last 16 weekly schedule-performance indices collected from all three project teams. The goal is to distinguish normal process variation (common causes) from unusual variation triggered by team-specific issues or external events (special causes). Which statistical quality-management tool will best help the Program Manager make this determination?

  • Control Chart

  • Scatter Diagram

  • Histogram

  • Pareto Chart

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot