A program to develop a new financial services platform is in the execution phase. A significant and unexpected regulatory change is announced, requiring substantial adjustments to the platform's compliance and reporting modules. The legal department has submitted a formal change request with wide-ranging impacts on program scope, schedule, and budget. What is the program manager's most appropriate initial action?

  • Approve the change in principle and charter a separate, fast-tracked project to handle the regulatory requirements to isolate the impact.

  • Initiate a comprehensive impact analysis across all program components, engaging with project teams and stakeholders to quantify effects on benefits, costs, risks, and the schedule.

  • Instruct the compliance module's project team to absorb the new requirements within their existing budget and timeline to demonstrate efficiency.

  • Immediately escalate the change request to the program governance board for a go/no-go decision to avoid any delays in resolution.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot