A program manager oversees a strategic initiative with several highly specialized component projects. Midway through the program, the manager notes that while individual project milestones are being met, there is little cross-component collaboration. To ensure benefit optimization and capture emergent synergies, what is the program manager's most effective next step?

  • Report the successful progress of the individual projects to the steering committee to maintain their confidence and secure continued funding for the program's completion.

  • Postpone integration efforts until the individual components are fully developed and tested to minimize rework and complexity during the final program phase.

  • Facilitate a series of workshops focused on integrating the components' benefit realization plans, tasking the teams to identify and map interdependencies that could create combined value.

  • Instruct each project manager to create a detailed risk register for their own component to prevent any single project from jeopardizing the program's overall success.

PgMP
Benefits Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot