A program manager needs to assess whether a project is staying within its budget by comparing the value of work completed to the actual costs incurred. Which performance analysis technique should the manager use?
Earned Value Analysis (EVA) is the appropriate technique as it integrates scope, schedule, and cost to provide a comprehensive view of project performance, allowing comparison of planned and actual expenditures.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is Earned Value Analysis (EVA)?
Open an interactive chat with Bash
How does EVA compare to other analysis techniques like SWOT?
Open an interactive chat with Bash
What are the key components of Earned Value Analysis?
Open an interactive chat with Bash
PgMP
Governance
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Oh snap!
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access