PgMP Practice Question

A program manager needs to assess performance by comparing the work completed and resources used against the plan. Which approach uses numerical indicators of both activity progress and resource consumption to reveal variances between actual outcomes and planned targets?

  • An approach that extrapolates past performance to predict future outcomes without a primary focus on integrating current cost and schedule variances.

  • An approach that prioritizes investigating the foundational reasons for delays but excludes integrated financial performance indicators.

  • An approach that applies quantitative measures to both completed work and resource utilization to highlight variances from the performance baseline.

  • An approach that organizes tasks in evolving phases for gradual definition but lacks an integrated cost-schedule performance view.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot