PgMP Practice Question

A program manager is presenting the program charter to the steering committee for approval. To best justify the program's investment and secure authorization, which element of the charter should be emphasized?

  • The resource allocation plan for the program management office.

  • A comprehensive register of all identified program risks.

  • A detailed breakdown of all constituent project schedules.

  • The program's expected benefits and alignment with strategic objectives.

PgMP
Strategic Program Alignment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot