PgMP Practice Question

A program manager is preparing to present the charter for a large-scale digital transformation program. A key executive sponsor insists on including detailed project-level budgets and specific resource assignments prior to the approval meeting. Another stakeholder argues this level of detail is premature and will delay authorization. What is the most appropriate action for the program manager?

  • Present two versions of the charter: one high-level version for the general leadership and a detailed version for the executive sponsor.

  • Escalate the conflicting stakeholder demands to the program governance board to mediate the dispute before the presentation.

  • Proceed with presenting the charter focusing on high-level costs, milestones, and benefits to secure formal authorization, and address detailed planning in the next phase.

  • Delay the charter presentation to incorporate the detailed project-level data as requested by the executive sponsor.

PgMP
Strategic Program Alignment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot