PgMP Practice Question

A program manager is preparing the program charter to secure formal approval from the program steering committee. According to PMI standards, which set of components is essential for this initial authorization document?

  • A complete list of all constituent projects, their approved project charters, and signed vendor contracts

  • A detailed program Work Breakdown Structure (WBS), responsibility assignment matrix (RAM), and the communications management plan

  • High-level program scope, key milestones, and a summary of expected benefits

  • The comprehensive benefits realization plan, benefits sustainment plan, and performance measurement baselines

PgMP
Strategic Program Alignment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot