PgMP Practice Question

A program manager is overseeing the closure of a five-year strategic transformation program. Several project managers, anxious to transition to new roles, have simply uploaded their final project files to various folders on a shared drive with no structure. To ensure long-term value and compliance, what is the program manager's most critical next step?

  • Consolidate all the unstructured files into a single master folder marked "Final Program Archives" to ensure the program can be closed by the deadline.

  • Ask each project manager to individually organize their files according to their best judgment before the final program review meeting.

  • Report the non-compliant project managers to their functional leads for failing to follow mandated closeout procedures.

  • Instruct the PMO to immediately implement the pre-defined archiving protocol, including metadata tagging and a structured repository, and then audit all component project archives for compliance.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot