PgMP Practice Question

A program manager is overseeing the closure of a complex, three-year strategic transformation program. Senior leadership is eager to reallocate the core team to a new, high-priority initiative and has requested an expedited closure process. How should the program manager best balance the need for speed with the responsibility of capturing and disseminating valuable program insights for organizational benefit?

  • Organize a formal, facilitated post-program review workshop with key stakeholders and the core team, documenting findings in the organization's knowledge management system before releasing the team.

  • Prioritize the immediate transition of operational sustainment and financial closure, scheduling the lessons learned review for a later date once the new initiative is stable.

  • Conduct a series of informal exit interviews with key team members and compile a summary report exclusively for the program sponsor.

  • Delegate the lessons learned documentation to individual project managers and aggregate their reports after the core team has transitioned to the new initiative.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot