PgMP Practice Question

A program manager is overseeing several projects that rely on common technical specialists. Two of the project managers cannot agree on how to allocate the same senior engineer’s time and have asked the program manager to intervene. Which approach is best for ensuring this conflict is resolved according to established governance processes and procedures?

  • Hold separate conversations with the project managers and override any established oversight procedure

  • Notify the governance board and document a resource escalation request based on standard guidelines

  • Postpone the decision until the next general leadership meeting instead of escalating it now

  • Reassign the engineer to the highest-paying project without consulting the governance board

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot