A program manager is leading a kick-off meeting for a new strategic program with a diverse group of key stakeholders, including executive sponsors. To most effectively secure their commitment and buy-in, which of the following should be the program manager's primary focus?

  • Articulating the program's vision and demonstrating its direct alignment with the organization's strategic objectives.

  • Detailing the initial risk register and the high-level risk mitigation strategies.

  • Presenting the high-level program roadmap, including major phases and key milestones.

  • Outlining the program's governance framework, including roles, responsibilities, and escalation paths.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot