A program manager is developing a detailed program scope statement. Which element is essential to include to effectively incorporate the program vision and facilitate overall planning?
External influences and variables impacting the program
Individual task assignments for team members
Detailed timelines for each project within the program
Including external influences and variables is crucial as it ensures the program scope aligns with the program vision and considers all factors that may impact the program. While detailed timelines and task assignments are important, they are more relevant to project-level planning. Daily operational procedures do not directly contribute to defining the program scope.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are external influences and variables in a program context?
Open an interactive chat with Bash
Why are external influences more important at the program level than detailed task assignments?
Open an interactive chat with Bash
How do external influences impact program scope management?
Open an interactive chat with Bash
PgMP
Program Life Cycle Management
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99 $5.99
$5.99/mo
Billed monthly, Cancel any time.
$9.99 after promotion ends
3 Month Pass
$19.99 $11.99
$3.99/mo
One time purchase of $11.99, Does not auto-renew.
$19.99 after promotion ends
Save $8!
BEST DEAL
Lifetime Pass
$29.99 $17.99
One time purchase, Good for life.
Save $12!
What You Get
All Project Management Package plans include the following perks and exams .