PgMP Practice Question
A program manager is coordinating a large-scale initiative with multiple subprojects that require the same specialized resources. The manager wants to minimize scheduling conflicts while meeting cost targets. Which action helps address these resource conflicts effectively?
Allow each manager to finalize their own resource estimates and adjust when conflicts emerge
Develop separate resource plans for each subproject without a unified assessment of shared resources
Create a matrix that maps skill requirements, timelines, and dependencies across the program
Maintain a short list of labor hours and roles for each subproject and distribute it to subproject managers