PgMP Practice Question

A program manager is assigned to a multi-year, enterprise-wide transformation program that is failing due to intense conflicts between key executives and widespread disengagement. To salvage the program, a new stakeholder engagement plan is required. Which initial action is most critical for analyzing the complex stakeholder landscape to build an effective strategy?

  • Conduct structured, one-on-one interviews with key stakeholders, including dissenting executives, to perform a detailed analysis of their interests, influence, and specific concerns.

  • Develop a new communications management plan based on the program's original stakeholder register and communication matrix.

  • Organize a large, all-hands workshop with all identified stakeholders to collaboratively redefine the program's vision and benefits.

  • Review all existing formal agreements, such as contracts and RFPs, to document the committed obligations of external partners and vendors.

PgMP
Stakeholder Engagement
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot