PgMP Practice Question

A program manager is approaching the end of the second of four planned phases. The program sponsor has expressed concerns about market changes that may impact the original business case. During the upcoming phase gate review, what should be the primary focus for the decision-making body?

  • Revalidating the program's alignment with strategic objectives and the continued viability of the business case.

  • Finalizing the resource allocation for the remaining phases of the program.

  • Reviewing the performance of the individual project managers within the program.

  • Approving the detailed work breakdown structure (WBS) for the next phase.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot