PgMP Practice Question

A program manager for a new strategic initiative reviews lessons learned from a similar past program, which revealed that poor stakeholder communication resulted in significantly diminished benefits realization. The organization's standard process is to archive these reports. What action should the program manager take to best ensure the new program's success?

  • Follow the standard PMO process by ensuring the report is archived and accessible to the new team.

  • Escalate the findings to the governance board and recommend delaying the new program until the organization's lessons learned process is improved.

  • Schedule a one-time kickoff presentation for the new team to review the key failures from the previous program's lessons learned report.

  • Formally update the new program's governance plan and communication strategy to include specific mitigation activities based on the identified lessons.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot