PgMP Practice Question

A program manager for a new enterprise resource planning (ERP) system implementation notices that operational readiness is lagging. While the technical deployment is on schedule, the long-term value is at risk because IT support and business unit teams are unprepared to manage the new system. What is the most critical integration activity to prioritize?

  • Secure additional funding to hire a specialized third-party firm for post-launch operational support.

  • Establish a joint working group with operational leaders to integrate new skill development and process handoffs into the program plan.

  • Request a scope change to delay the final go-live date until operational teams declare full readiness.

  • Launch an internal communications campaign to highlight the upcoming changes and benefits to all employees.

PgMP
Strategic Program Alignment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot