PgMP Practice Question

A program manager for a multi-year technology transformation finds that cost and schedule are tracking 5% ahead of plan. However, a key KPI for a recently deployed component-user adoption-is 20% below target, jeopardizing long-term benefits. The program sponsor, focused on the positive financial metrics, wants to accelerate the next phase. What is the program manager's most critical next step?

  • Escalate the conflicting performance data to the steering committee and request their decision on whether to prioritize speed or user adoption.

  • Initiate a root-cause analysis on the low user adoption, engaging business and project stakeholders to assess the impact on the benefits realization plan.

  • Authorize the closure of the component project since it met its technical scope and schedule, and document the adoption issue as a lesson learned.

  • Re-allocate the budget surplus to the program's next phase to leverage the schedule gains as requested by the sponsor.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot