PgMP Practice Question

A program is undergoing a formal phase gate review. The program manager has presented the status of component projects, including performance metrics and risk assessments. What is the primary focus of the program governance board during this review?

  • Analyze the detailed performance of individual projects against their cost and schedule baselines.

  • Approve or reject pending change requests that have been escalated from component projects.

  • Ensure that lessons learned from the previous phase have been documented in the knowledge repository.

  • Assess the program's continued business justification and alignment with strategic objectives.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot