A program comprises five interdependent projects. At the mid-year steering-committee review, the CFO requests a single dashboard metric that objectively integrates scope completion, schedule progress, and cumulative costs so executives can judge whether the overall program is delivering value for money. Which performance analysis technique should the program manager recommend implementing across all projects?

  • Benefits Realization Tracking

  • Critical Path Method

  • Balanced Scorecard

  • Earned Value Analysis

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot