A multinational infrastructure program requires specialized equipment and materials to arrive at multiple construction sites exactly when needed, while keeping inventory levels and handling costs low. Which program management focus area is primarily responsible for planning, implementing, and controlling the efficient flow and storage of these physical resources from their point of origin to each site to support the program's objectives?

  • Logistics management

  • Quality assurance management

  • Benefits realization management

  • Stakeholder engagement management

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot