PgMP Practice Question

A manufacturing program with eight interdependent projects is generating inconsistent cost and schedule metrics because each project uses a different software platform and data taxonomy. Senior executives have asked for a single source of truth that gives them real-time visibility across the program. As program manager, which action best addresses this request while aligning with program-governance expectations?

  • Issue a common reporting template but allow each project to continue using its own software with no data integration

  • Implement a program management information system that integrates all project tools, applies shared data standards, and generates consolidated dashboards for stakeholders

  • Hold a standing status meeting where project managers verbally reconcile their metrics each reporting cycle

  • Assign a dedicated analyst to collect status updates by email and compile a monthly spreadsheet dashboard

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot