A manager wants to ensure each project under a program follows the same approach for cost, schedule, and quality reporting. Which action best meets this goal?
Coordinate different methods for each project based on unique circumstances
Use a flexible framework that allows each project to change performance metrics
Rely on external consultants to determine each project’s reporting needs
Adopt recognized standards that define a uniform oversight and measurement approach
Recognized standards unify the structure across all projects, guiding teams to use common methods for tracking cost, schedule, and quality. Having each project create its own strategy or relying on external processes may lead to conflicts or misalignment. Using a single flexible model also risks differing interpretations without an agreed foundation aligned with industry and organizational practices.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are recognized standards in project management?
Open an interactive chat with Bash
Why is uniform oversight important in program management?
Open an interactive chat with Bash
How can conflicting reporting methods impact a program?
Open an interactive chat with Bash
PgMP
Governance
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access