Multistate Bar Examination Practice Question

A homeowner and a builder entered into a written contract for the construction of a new house, with a completion date of October 1. The contract included a clause stating that for each day the house was not complete after October 1, the builder would pay the homeowner $1,000. At the time of contracting, it was difficult to estimate the precise damages the homeowner might suffer from a delay, but both parties believed $1,000 per day was a reasonable estimate, considering potential costs for temporary housing, storage, and other inconveniences. The builder completed the house on October 31, a 30-day delay. The homeowner's actual damages due to the delay amounted to approximately $950 per day. The homeowner has sued the builder to enforce the daily damages clause.

How is a court most likely to rule on the liquidated damages clause?

  • The clause is enforceable only up to the actual damages of $950 per day, with the remaining $50 per day being an unenforceable penalty.

  • The clause is enforceable because the amount is a reasonable forecast of the harm caused by the breach.

  • The clause is unenforceable because its primary purpose was to penalize the builder for being late.

  • The clause is unenforceable because the liquidated amount of $1,000 per day is not identical to the actual damages of $950 per day.

Multistate Bar Examination
Contracts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot