Multistate Bar Examination Practice Question

A contractor entered into a written agreement to build a shed for a homeowner for $20,000. Partway through construction, the contractor realized they had underbid the project and ran out of funds. The contractor notified the homeowner that they could not complete the project. The homeowner hired another contractor to finish the shed, spending $9,000 for completion. The partially completed shed had a value of $10,000, and the homeowner had paid the contractor $7,000 before construction stopped. What amount, if any, is the original contractor entitled to recover despite breaching the contract?

  • The contractor is entitled to recover $2,000, representing the difference between the $9,000 cost of completion and the amount previously paid by the homeowner.

  • The contractor is entitled to recover $10,000 for the value of the partially completed shed.

  • The contractor is not entitled to recover anything because they breached the contract.

  • The contractor is entitled to recover $3,000 in restitution for the value of the benefit conferred on the homeowner, net of payments already received.

Multistate Bar Examination
Contracts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot