An organization's disaster recovery plan states that the maximum amount of data they can tolerate losing is 3 hours’ worth of work. Which term best describes this criterion?
RPO
MTTR
RTO
DLP
An organization's disaster recovery plan states that the maximum amount of data they can tolerate losing is 3 hours’ worth of work. Which term best describes this criterion?
RPO
MTTR
RTO
DLP
Recovery Point Objective (RPO) is defined as the maximum targeted period in which data might be lost from an IT service due to a major incident. The correct answer Recovery Point Objective (RPO) directly matches the definition described in the question, where a company determines how much historical data can be lost without severely impacting business continuity. Recovery Time Objective (RTO), while critical, is concerned with the duration it takes to recover after a disruption, not the amount of data lost. Mean Time to Repair (MTTR) is related to repairs, not data loss, and Data Loss Prevention (DLP) is a strategy to prevent data breaches, not a metric related to acceptable data loss in disaster scenarios.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.