Free CompTIA Network+ N10-008 Practice Question

Your organization has experienced a significant outage due to a natural disaster, and critical data was lost. In the aftermath, the company reevaluates its backup and recovery strategy to minimize data loss in the event of future disasters. Which of the following metrics should be primarily adjusted to ensure that the maximum acceptable amount of data loss measured in time is not exceeded in future incidents?

  • Password policy should be updated to prevent data loss.

  • Recovery Time Objective (RTO) should be shortened.

  • Recovery Point Objective (RPO) should be reduced.

  • Network Interface Card (NIC) teaming strategy should be revised to ensure redundancy.

This question's topic:
CompTIA Network+ N10-008 / 
Network Operations
Your Score:

Check or uncheck an objective to set which questions you will receive.