ISC2 Governance, Risk and Compliance (CGRC) Practice Question

You are creating the timeline section of a control-implementation plan for a new payment-processing system. To set realistic milestones, you must determine which tasks have to finish before others can begin (for example, configuring an identity vault before enabling single sign-on). Which scheduling technique will most effectively reveal these task dependencies and the minimum overall project duration?

  • Sprint retrospective meetings

  • Earned value analysis (EVA)

  • Monte Carlo simulation of schedule risk

  • Critical path method (CPM) network analysis

ISC2 Governance, Risk and Compliance (CGRC)
Implementation of Security and Privacy Controls
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot