ISC2 Governance, Risk and Compliance (CGRC) Practice Question

While drafting the implementation strategy for a new cloud-based payroll system, the control implementation lead must clearly indicate which team members will be Responsible, Accountable, Consulted, or Informed for each selected NIST 800-53 control. Which project artifact best satisfies this resourcing need?

  • Create a RACI matrix that lists each control and assigns Responsible, Accountable, Consulted, and Informed parties.

  • Enter the selected controls and owners into the project's risk register for ongoing monitoring.

  • Establish a configuration baseline that documents approved system settings for each control.

  • Develop a Gantt chart showing start and finish dates for all control-related tasks.

ISC2 Governance, Risk and Compliance (CGRC)
Implementation of Security and Privacy Controls
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot