ISC2 Governance, Risk and Compliance (CGRC) Practice Question

During the Testing phase of the SDLC, a project team must demonstrate that the selected security controls operate as intended before moving to production. Which activity best meets this objective for an information system undergoing RMF authorization?

  • Draft the system security plan to document applied and inherited controls

  • Populate the continuous-monitoring strategy with event-driven triggers

  • Conduct an independent security control assessment in a representative test environment

  • Develop configuration baseline documentation for approved changes

ISC2 Governance, Risk and Compliance (CGRC)
Security and Privacy Governance, Risk Management, and Compliance Program
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot