ISC2 Governance, Risk and Compliance (CGRC) Practice Question

During a major system upgrade, your organization requires that both a Change Control Board (CCB) and a Technical Review Board (TRB) participate in the approval workflow. Before the request can be presented to the CCB, which primary activity should the TRB complete?

  • Issue the formal authorization that allows the change to proceed into production.

  • Evaluate the change for technical feasibility and security-baseline impacts, documenting identified risks.

  • Notify auditors of the approved change and archive the final change record for compliance purposes.

  • Assign business priority and select an implementation window for the production environment.

ISC2 Governance, Risk and Compliance (CGRC)
Compliance Maintenance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot