ISC2 Governance, Risk and Compliance (CGRC) Practice Question

After completing a security control assessment, the project team discovers two moderate vulnerabilities that cannot be fixed before the system's upcoming authorization to operate (ATO). They need a formal record that identifies each weakness, assigns a responsible party, and establishes interim milestones for remediation. Which document should they update to capture this residual risk and planned corrective actions?

  • Contingency plan

  • Risk register

  • Configuration management plan

  • Plan of Action and Milestones (POA&M)

ISC2 Governance, Risk and Compliance (CGRC)
Implementation of Security and Privacy Controls
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot