A data analyst has just presented the final version of a new marketing dashboard to the department head. After incorporating all requested changes, the department head has confirmed the dashboard meets the initial business requirements. What is the immediate next milestone that must be completed before the dashboard can be deployed for wider use?
The data engineering team releases the next version or iteration
Preparing a detailed reference guide for end users
Aligning data sets to an enterprise naming standard
Collecting sign-off from the appropriate decision makers
After stakeholders confirm that a dashboard mockup or final version meets business requirements, formal approval or sign-off is the crucial milestone before it can be deployed. While creating user guides, standardizing data, and releasing new versions are all part of the overall process, the formal approval signals that the project has met its objectives and can proceed to the next stage.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the role of decision maker sign-off in project milestones?
Open an interactive chat with Bash
Why isn’t preparing user guides considered a milestone for readiness?