CompTIA CySA+ CS0-003 Practice Question
Your organization has identified a security vulnerability in an internally developed application. After performing a risk assessment, it is determined that the cost of remediation exceeds the potential impact of the vulnerability being exploited. Additionally, there is no immediate threat or known exploit for this vulnerability. What is the MOST appropriate risk management response in this scenario?
Transfer the risk by outsourcing the application component to a third-party vendor.
Formally accept the risk and monitor for changes in the threat landscape.
Patch the vulnerability immediately regardless of the remediation costs.
Schedule the patch to be included in the next release cycle without additional review.