You have submitted a change request for a firmware upgrade on a core switch. Business leadership has approved the maintenance to occur after normal business hours. Which timing detail must be included in the change record so that all stakeholders know exactly when the network will be unavailable?

  • Expected length of the maintenance window

  • Projected date for the post-implementation review

  • Time zone in which the change will be executed

  • Scheduled start date and exact time of the change

CompTIA A+ 220-1202 (V15)
Operational Procedures
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $32
CompTIA A+ Voucher
v15 / 220-1201 / 220-1202
$265.00 $233.00
SAVE $38
CompTIA A+ Voucher with Retake
v15 / 220-1201 / 220-1202
Includes Retake
$314.00 $276.00
Bash, the Crucial Exams Chat Bot
AI Bot