CompTIA A+ 220-1102 Practice Question
Which part of the change management process involves evaluating how the change will affect the company if the change is made?
Scope of the change
Request forms
Risk analysis
Purpose of the change
Which part of the change management process involves evaluating how the change will affect the company if the change is made?
Scope of the change
Request forms
Risk analysis
Purpose of the change
During the change management process, a risk analysis is used to determine the risk if the change is allowed to take place. After the risk analysis, the results of the analysis are used to make the decision on whether or not to allow the change.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Information Technology Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All Information Technology Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.