CompTIA A+ 220-1102 Practice Question
This is the part of the change management process where the change is tested by the actual users to verify that it works for the user.
Change board approval
Risk analysis
End-user acceptance
Change request
This is the part of the change management process where the change is tested by the actual users to verify that it works for the user.
Change board approval
Risk analysis
End-user acceptance
Change request