CompTIA A+ 220-1102 (V14) Practice Question

A company plans to upgrade the desktop operating system on every employee workstation next month. To assess how this change could disrupt day-to-day work, which of the following information should the IT team gather FIRST?

  • List of approved mobile devices connected through MDM

  • Inventory of installed applications on the workstations

  • Current UPS battery runtime for each branch office

  • Peak network bandwidth utilization during business hours

CompTIA A+ 220-1102 (V14)
Operational Procedures
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $32
CompTIA A+ Voucher
v14 / 220-1101 / 220-1102
$265.00 $233.00
Bash, the Crucial Exams Chat Bot
AI Bot